Premier Christy Clark has written to the NDP and Green Party leaders, warning that a delay in removing two homes from the path of a Site C dam road could delay the project by a year and cost as much as $600 million.
In letters released Tuesday, Clark asked both NDP leader John Horgan and B.C. Green Party leader Andrew Weaver to reconsider Horgan香蕉视频直播檚 request to delay the removal of two homes on land expropriated by BC Hydro for the third dam on the Peace River.
A decision must be made by June 15 on whether to proceed, Clark wrote. Her letters also ask:
香蕉视频直播溝憬妒悠抵辈ウwhether or not you would like government to issue a 香蕉视频直播榯ools down香蕉视频直播 request to BC Hydro on the other decisions that are essential in maintaining the budget and construction schedule of the Site C Clean Energy Project, given that the project is likely to progress past the 香蕉视频直播榩oint of no return香蕉视频直播 before the B.C. Utilities Commission review you have suggested could be reasonably concluded.香蕉视频直播
Horgan responded Tuesday, calling Clark香蕉视频直播檚 claims of cost escalation 香蕉视频直播渦nsupported香蕉视频直播 and accusing the B.C. Liberals of driving up BC Hydro bills due to 香蕉视频直播渕ismanagement香蕉视频直播 of the project.
Weaver also responded to Clark香蕉视频直播檚 letter Tuesday, saying he would need access to official documents on the project before he could respond to her questions.
Horgan wrote to BC Hydro CEO Jessica McDonald May 31 to ask for a lease extension for two families, including Peace Valley Landowner Association members Ken and Arlene Boon, whose homes are on a road right-of-way needed for the dam.
香蕉视频直播淚 believe there is no demonstrated short-term need to force these families from their homes, and because the status of the next governments of British Columbia are uncertain, the threat of imminent removal of residents from their expropriated homes and property is unreasonable,香蕉视频直播 Horgan wrote.
Clark香蕉视频直播檚 letter says 香蕉视频直播渢he relocation of the homes in question is necessary as part of a two-year road and bridge construction project that will enable river diversion to occur in September 2019.香蕉视频直播
River diversion has to be done when water is low in summer, not in winter when the two existing Peace River dams are running water through turbines to supply winter electricity demand.
香蕉视频直播淧reliminary work undertaken on this issue by BC Hydro indicates that should river diversion not be completed as scheduled, a year-long delay would occur in order to divert the river during the next low-flow period, in September 2020,香蕉视频直播 Clark wrote. 香蕉视频直播淭his one-year delay is estimated to cost ratepayers $600 million.香蕉视频直播
香蕉视频直播淕iven the obligation that BC Hydro has in place with respect to road construction and completion, a decision to proceed will need to be made no later than June 15, 2017 in order to maintain the September 2019 river diversion schedule.香蕉视频直播
Weaver responded to Clark香蕉视频直播檚 letter Tuesday, saying he would need access to official documents on the project before he could respond to her questions.