West Kelowna residents will soon have a clearer picture of the final cost of the new city hall.
香蕉视频直播淎 complete and final accounting of the city hall project should be done by the end of January,香蕉视频直播 Chief Financial Officer Warren Everton told council during budget deliberations on Dec. 18.
The building, which opened in May, currently carries a price tag of $22.79 million香蕉视频直播攚ell above its original $18 million budget. Construction delays and supply chain disruptions extended the project timeline.
Council also heard that in council chambers. Another $85,000 will go toward designing parking lot improvements. Both projects will be funded through the city香蕉视频直播檚 capital reserves.
Staff also requested $278,000 to replace outdated audio and visual equipment in council chambers. This equipment had been brought over from the former municipal facility at the Mount Boucherie Community Centre.
香蕉视频直播淚t is getting outdated and in need of replacement,香蕉视频直播 Everton explained. 香蕉视频直播淲e香蕉视频直播檝e had certain issues with it since we香蕉视频直播檝e brought it here.香蕉视频直播